Nuozhadu Dam
Nuozhadu Dam | |
---|---|
Location | Puer, Yunnan Province |
Coordinates | 22°39′22″N 100°25′06″E / 22.65611°N 100.41833°E |
Status | Operational |
Construction began | 2004 |
Opening date | 2012 |
Dam and spillways | |
Type of dam | Embankment, central core, rock-fill |
Impounds | Lancang (Mekong) River |
Height | 261.5 m (858 ft) |
Length | 608 m (1,995 ft) |
Width (crest) | 18 m (59 ft) |
Spillway type | Service, controlled side channel chute |
Spillway capacity | 31,318 m3/s (1,106,000 cu ft/s) |
Reservoir | |
Creates | Nuozhadu Reservoir |
Total capacity | 21,749,000,000 m3 (17,632,000 acre⋅ft) |
Catchment area | 140,000 km2 (54,000 sq mi) |
Surface area | 320 km2 (120 sq mi) |
Power Station | |
Commission date | 2012-2014 |
Hydraulic head | 187 m (614 ft) |
Turbines | 9 x 650 MW Francis-type |
Installed capacity | 5,850 MW |
Annual generation | 23,9 TWh[1] |
Nuozhadu Dam (Chinese: 糯扎渡大坝; pinyin: Nuòzhādù Dàbà) is an embankment dam on the Lancang (Mekong) River in Yunnan Province in southwest China. The dam is 261.5 m (858 ft) tall, and creates a reservoir with a normal capacity of 21,749,000,000 m3 (17,632,000 acre⋅ft) at a level of 812 m (2,664 ft) asl. The purpose of the dam is hydroelectric power production along with flood control and navigation. The dam supports a power station with nine generators, each with generating capacity of 650 MW. The total generating capacity of the power station is 5,850 MW.[2] Construction on the project began in 2004; the dam's first generator went online 6 September 2012 and the last generator was commissioned in June 2014.[3][4] The construction and management of the project was implemented by Huaneng Power International Ltd., which has a concession to build, own and operate hydroelectric dams on China's stretch of the Mekong River.
See also
[edit]- List of power stations in China
- List of tallest dams in the world
- List of tallest dams in China
- List of dams and reservoirs in China
References
[edit]- ^ "Largest hydropower station on Mekong River starts operation - Xinhua | English.news.cn". Archived from the original on 2014-08-26. Retrieved 2014-08-27.
- ^ "Nuozhadu Hydropower Project" (PDF). Chinese National Committee on Large Dams. Retrieved 6 January 2011.
- ^ "Yunnan's largest hydroelectric dam goes online". Go Kunming. Archived from the original on 6 January 2019. Retrieved 15 May 2013.
- ^ Harris, Michael. "Last turbine unit in operation at Chian's 5,850-MW Huaneng Nuozhadu hydropower plant". Hydro World. Retrieved 19 November 2014.
- Zhang Zhonglan and Yuan Youren: Slope stability study and section optimization of Nuozhadu’s earth core rockfill dam, New Developments in Dam Engineering. Proceedings of the 4th International Conference on Dam Engineering, 18-20 October 2004, Nanjing, China[permanent dead link ]
- Nuozhadu Hydropower Project - Excavation of the Underground Powerhouse Complex
- Hydroelectric power stations in Yunnan
- Dams in China
- Dams in the Mekong River Basin
- Dams completed in 2012
- 2014 establishments in China
- Energy infrastructure completed in 2014
- China Huaneng Group
- Buildings and structures in Pu'er
- Asian dam stubs
- Hydroelectric power plant stubs
- People's Republic of China power station stubs