HomeMajor ProjectsConstruction Advertisement Plan (CAP) → Construction Advertisement Schedule

Construction Advertisement Schedule

  1. The Construction Advertisement Schedule is refreshed every Monday.
  2. Below is the current schedule performance, outlining the current status of all projects included in the annual Construction Advertisement Plan, as well as any projects that have been added to the schedule this year (PDF below).
  3. A Current Schedule Performance chart, based on the annual Construction Advertisement Plan, published in January of each year
  4. The Glossary describes the change status and work types used in the Advertisement Schedule.

Searchable Project Map

View our searchable Project Map to find projects by town or county.

Downloads

If you have a problem accessing this data, please contact Andy Bickmore at 624-3293 or by email.

Updated Construction Advertisement Schedule
Work TypeAdvertise DateScopeLocation/TitleDetailsProject
Identification No.
Administered ByTotal Project Estimate
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Current Schedule Performance

Status of Projects in Plan =  

 
 

Status of Projects Added =  

 
 
Glossary

Work Type Descriptions

Work TypeDescription
Bridge ConstructionConstruction, replacement or major rehabilitation of traditional bridges and minor spans that are not culverts, including superstructure and deck replacements.
Bridge OtherAll other bridge projects, including preservation and replacement of large culvert-like structures defined as bridges or minor spans.
Highway ConstructionConstruction on new alignment, reconstruction, or major rehabilitation of a road corridor that generally involve changes to the alignment or width of the road. Sometimes known in the industry as "dirt jobs".
Highway Safety and Spot ImprovementsIntersection and ramp improvements, as well as signing, lighting, striping, etc. May include substantial, higher cost, intersection construction projects.
Highway Preservation PavingAll pavement preservation or rehabilitation treatments of higher priority roads, designed to maintain a higher level of service and avoid the higher cost of reconstruction. The useful life of such treatments is generally 10 years or more. Does not include Light Capital Paving (see below).
Highway Light Capital Paving (LCP)A thin pavement treatment to keep poor, generally lesser traveled roads serviceable. The useful life of LCP paving is about 4 to 7 years. Formerly known as Maintenance Surface Treatment (MST) or "skinny-mix".
MultimodalRail, transit, airport, marine, and bicycle/pedestrian projects.

Status Descriptions

StatusDescription
Advertised On TimeProject is in the annual plan and was advertised within 29 days of planned date.
On TimeProject is in the annual plan, not yet advertised, and the current forecast advertise date is within 29 days of the planned date.
Advertised LateProject is in the annual plan and was advertised 30 days or more after the planned date.
Merged with Other WorkProject is part of the annual plan and now included in the scope of another project in order to reduce administrative costs.
Removed from ScheduleProject was in the annual plan but has been removed from the schedule.
DelayedProject is in the annual plan and the current advertisement forecast date is 30 days or more after the planned date, or, there is no actual advertisement date within 29 days of the planned date.