0% found this document useful (0 votes)
15 views2 pages

Tanay Rizal Apartment

Uploaded by

hulogmonthly
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
Download as xlsx, pdf, or txt
0% found this document useful (0 votes)
15 views2 pages

Tanay Rizal Apartment

Uploaded by

hulogmonthly
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1/ 2

Date : February 26, 2024

Project : Repair of Two Storey Apartment


Location : Tanay, Rizal
Subject : Quotation
Validity : February 29, 2024

Unit Materials Labor


Item Descrition Qty Total Cost
Unit Cost Total Cost Unit Cost Total Cost

1.00 Site Preparation


Mobilization and demobilization 1.00 ls - - 10,000.00 10,000.00 10,000.00
Installation of scaffolding 1.00 ls - - 2,500.00 2,500.00 2,500.00
Dismantling of scaffolding 1.00 ls - - 2,500.00 2,500.00 2,500.00

Removal of existing windows (lower part only) 1.00 ls - - 1,500.00 1,500.00 1,500.00

Chipping and restoration of concrete column


1.00 ls - - 1,500.00 1,500.00 1,500.00
outside the boundary line
- - -
2.00 Masonry Works - - -
Chb layering 4" thick 8.00 sq.m 450.00 3,600.00 250.00 2,000.00 5,600.00
Plastering works 16.00 sq.m 150.00 2,400.00 250.00 4,000.00 6,400.00
- - -
3.00 Waterproofing/painting Works 45.00 sq.m 250.00 11,250.00 150.00 6,750.00 18,000.00
- - -
4.00 Sanitary Works - - -
Rectification of vent thru pipe 1.00 ls 2,500.00 2,500.00 2,000.00 2,000.00 4,500.00
Repair of damaged pipe 1.00 ls 1,000.00 1,000.00 1,500.00 1,500.00 2,500.00

Materials ₱ 20,750.00
Labor ₱ 34,250.00
Profit ₱ 8,250.00
Grand Total ₱ 63,250.00

Prepared By: Daniel M. Priela RCE